​Galaxy Middle - Campus Wide HVAC, Lighting, Ceiling - Project No. 174589
Construction Management Solicitation Questions / Responses

Question:
Received October 27, 2016
​Regarding the Galaxy MS proposal, per the discussions a the mandatory pre-submittal meeting, (1) we understand VCS is limiting the work to one classroom building at a time.
We understand VCS will provide portables to be used as temporary classrooms during the project. This is not indicated in the pre-submittal minutes prepared by VCS. (2) Can you please confirm how much area is available for construction at any given time?
Response:
Published October 28, 2016
​(1) Please reference the pre-submittal meeting minutes, page 1 of 2, first question at the bottom of the page "... District will provide portables to empty a building at a time over the duration of the project."
(2) The intent is to make classroom buildings 3,4 & 6 available one at a time during the school year for construction. The appoximate area of each building is 22,750 sq. ft. As each building is completed and occupied, the next classroom building will be vacated and readied for construction. The following buildings will be available for construction during the summer months when school is not in session.
Building 1 - Administration, approximately 2,900 sq. ft.
Building 2 - Dining / Multi-Purpose, approximately 20,800 sq. ft.
Building 5 - Vocational, approximately 8,600 sq. ft.
Building 7 - Media Center / Home Ec. / Business, approximately 19,500 sq. ft.
Building 8 - Art, approximately 4,600 sq. ft.
Building 9 - Gym / Locker Rooms, approximately 19,800 sq. ft.
Building 10 - Band / Chorus, approximately 9,600 sq. ft.
Building 11 - Central Receiving, approximately 1,800 sq. ft.