​​Chisholm Elementary, Replacement School, Project No. 174540
Construction Management Services Solicitation Questions / Responses

​Question
Received March 22, 2017
​Are there plans to preserve the existing basketball and/or tennis courts?
​Response
Published March 23, 2017
This is not known at this time.


​Question
Received March 22, 2017
​There appears to be a fiberglass housing structure in front of the admin buildling, are you able to tell us what this is?
Response
Published March 23, 2017
The fiberglass housing contains the backflow preventer.


​Question
Received March 22, 2017
​Has there been an asbestos survey completed recently?
Response
Published March 23, 2017
We do not have a recent asbestos survey for Chisholm Elementary.


​Question
Received March 22, 2017
​Can you provide an as-built of the existing site utilities?
Response
Published March 23, 2017
Click here to access the as built survey.


​Question
Received March 22, 2017
​Can you provide a site-plan?
Response
Published March 23, 2017
No, there is not a final site plan at this time.


​Question
Received March 22, 2017
​Who is the civil engineer for this project?
Response
Published March 23, 2017
Zev Cohen & Associates who are a sub-consultant to Rhodes + Brito Architects.